City Rail Link construction

Following the construction of the City Rail Link between Britomart and Mt Eden, from enabling works to project completion
383 photos in this gallery. Showing photos 361 - 383

The new platforms at Mt Eden are taking shape, with the station building rising above all four platforms under construction

3 March 2023

AM 618 passes through the middle of the construction site, giving an impression on what the future looks like

3 March 2023

At Porters Ave, the footbridge has now fully opened with functioning lifts

4 June 2023

On the western side of the bridge, the ballast formation for the NIMT tracks is in place from the trench to the turnouts on the NAL. Of note is the All Trains Stop board within the trench, indicating the tunnel is "dark" to Train Control until signalling work is completed though Martinus construction trains can still use the tracks

4 June 2023

Porters Ave has now been repaved and turned into a proper dead-end street, though retaining access for businesses to the right

4 June 2023

Both tracks are now in place through the Mt Eden station site, although the Up Main is not yet fully signalled

4 June 2023

With tunnel boxing into the Newton junction box now complete, the tunnel portal is being backfilled, with the crew's hard work being buried forever

4 June 2023

Resting between jobs, Martinus's Zephir hi-rail locomotive sits on the link track coupled to a UKB wagon. Through here, both the Up and Down mains on the NAL are completed, and pinch together to pass under Mt Eden Road before moving apart again for the platform on the other side

4 June 2023

At Maungawhau (Mt Eden), more of the station building ha appeared, with all stair access to the original platform now in place and the station building taking shape

16 July 2023

On the other side of Mt Eden Road, both the Up and Down mains are now operational, with the Down link track mostly complete at this point

16 July 2023

Heading into the newly completed trench, AM 836 runs a service to Swanson on the Up main, now fully open

16 July 2023

Just seconds later after passing underneath Normanby Road, AM 415 exits the trench shortly before arriving at Grafton station. For the first time since temporary single tracking in 2020, two trains passed each other in the Mt Eden vicinity

16 July 2023

AM 415 passes the not-yet-in-use link track into the City Rail Link connecting to the North Island Main Trunk, with the operational Up Main on the other side of the trench. The sign requiring trains to get permission from Train Control relates to the link track, with normal signalling applying on the Up and Down mains

16 July 2023

With excavation and track work in the area now complete, Boston Road has had streetscaping completed and returned to two-way operation. All roads in the area are now fully open

3 January 2024

The reopening of Boston Road has enabled this shot of the Normanby Road overbridge, with all three tracks running underneath

3 January 2024

With track works now largely complete and key works moving underground, construction on Maungawhau station's landscaping and road networks has begun

3 January 2024

The station building for Maungawhau inches closer to completion, looking more like a station every day

3 January 2024

Further up the line, the Karanga-a-Hape station building rises from Mercury Lane

3 January 2024

The Beresford Square entrance to the station, on the other side of Karangahape Road, is also taking shape, although not much is visible from the surface

3 January 2024

Inside Waitematā (Britomart) station, the former Platform 2 has been decommissioned in advance of the City Rail Link opening. The in situ and now un-numbered platform is seen here with passengers disembarking from a train on Platform 1

9 March 2024

Out the back of Waitematā, the temporary entrance that was built for CPO works has now been demolished, now that it is no longer required for Martinus works in the area. The space is planned to be reinstated as a plaza by Auckland Council

9 March 2024

View of the renumbered platforms from the escalators at Waitematā. The former Platform 2 is now not numbered, with the other platforms moving down a number to fill the hole. Platforms 1 and 4 will be widened to handle the lager number of passengers coming in from the City Rail Link

9 March 2024

The new Platform 4 has now been extended and appears to be long enough for 9-car trains. The platform is seen here heading into the tunnel, with tracks now laid all the way through to the other end at Maungawhau

9 March 2024

Search
Sort
Licencing
Creative Commons License
All photos and videos on this site are licensed under a Creative Commons Attribution-NonCommercial-NoDerivatives 4.0 International License.
Attribution to https://nzrailphotos.co.nz is required. If you wish to use photos for commercial use or for an exception to this licence, please seek permission first. Fees may apply.